Project Description
Project Description
Boilerhouse & Heating Upgrade, Castletown Kinneigh Co. Cork
ASMS were the PSCS for this project with responsibility for the Mechanical, Electrical and Civil works associated with the project. The project entailed a complete heating upgrade consisting of a new Plantroom, LPHW system pipework and all associated controls.
Mechanical Installation works for this project include the following:
- Complete strip out of existing boiler house and Church LPHW system
- Installation of boiler, flue and circulating pump
- Complete electrical installation
- BMS
- Installation of new LPHW system in the Church
- Installation of Radiators
- Commissioning / Balancing
Project Details
Architect:
Consulting Engineers: John Kelleher & Associates
Main Contractors: ASMS Acting PSCS
Duration: 4 Weeks